By 21 November 2024, extensive desktop and data-driven studies had mapped key seabed and environmental constraints for the Nederwiek wind farm zone, including Nederwiek III, with Svašek Hydraulics delivering morphodynamics and scour and scour-protection analyses, complemented by UXO, geological, and archaeological desk studies for Nederwiek I, II, and III, which were presented in a dedicated webinar. [Mirrored from sibling Nederwiek III-A (69f4bf99e60465b367d612fb) on 19 May 2026 — shared pre-split history. This event materially applies to both Nederwiek III-A and Nederwiek III-B under the 3a/3b split formalised by the 31 March 2026 Kamerbrief on the LionLink offshore bidding zone.]