Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Year-precision projection — turbine installation likely to commence in 2032. Inferred from the 2032 first-power anchor stated by RVO via offshorewind.biz, 6 April 2026: "The wind farms are likely to start generating energy from 2032." Reasoning: in a 1 GW Dutch offshore wind build, turbine installation typically begins 2-6 months before first power as foundations are completed and inter-array cabling is energised. The kavelbesluit Regulation 3.3 requires three-bladed turbines of at least 15 MW (project intent at the next-generation 15-21 MW class). With first power anchored to 2032, turbine installation will most plausibly begin in 2032 and continue into 2033. No explicit turbine-installation date has been published for Gamma-A (developer not yet selected); this is an inferred placeholder. Confidence is low-to-moderate (~0.5).