Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Following an August 2025 amendment to the IJmuiden Ver Site Beta permit and publication of an authorisation agreement detailing the two construction phases and revised system-integration and payment obligations, the Zeevonk permit for IJmuiden Ver Beta became irrevocable on 17 October 2025, making the development rights for the phased 2 GW Zeevonk offshore wind project legally secure. [Mirrored from IJmuiden Ver Beta-1 sibling project (69f4b9e28673ef38ffe4fb7b) — shared pre-split history. This event materially applies to both Phase 1 and Phase 2 of the Beta permit under the Wijzigingsbesluit of 6 Aug 2025.]