Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Phase 2 of IJmuiden Ver Beta (Zeevonk) — the remaining approximately 1,001 MW required to reach full 2 GW commercial operations — must be ready to deliver power for grid testing by 30 November 2032 under the Wijzigingsbesluit dated 6 August 2025 (Staatscourant 2025, 28710). The phased delivery profile was agreed by the Dutch government and Zeevonk (Vattenfall + Copenhagen Infrastructure Partners) to address the delay of the Delta Rhine Corridor hydrogen pipeline. Hitting this deadline delivers Zeevonk's full 2 GW commercial operations milestone via the TenneT 2 GW HVDC connection to Maasvlakte.