Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
In January 2025, Fugro began an offshore geophysical survey programme for Vattenfall at the IJmuiden Ver Beta (Zeevonk) wind farm site in the Dutch North Sea. The campaign mobilised the survey vessel M/V Kommandor Iona and acquired analogue geophysical datasets supported by dual Eiva Scanfish III arrays. The programme also incorporated UXO survey works as part of the analogue scope to identify and manage potential unexploded ordnance hazards within the site and along relevant corridors. CP Geo-Services Ltd provided offshore client representative support, supervising operations and performing QC/QA on behalf of Vattenfall. The survey supported development-stage decision-making by providing the geophysical evidence base needed for layout refinement, constraints mapping and risk reduction ahead of foundation and cable installation activities under the phased Zeevonk delivery plan.