Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Phase 1 of IJmuiden Ver Beta (Zeevonk) — approximately 1,062.6 MW of offshore wind capacity — must be ready to deliver power for grid testing by 30 November 2029 under the Wijzigingsbesluit dated 6 August 2025 (Staatscourant 2025, 28710). This regulatory deadline aligns with Zeevonk's stated Phase 1 commissioning target and the TenneT grid connection delivery schedule in the Ontwikkelkader windenergie op zee (January 2026 update), and represents the project's first_power milestone — Phase 1 first export to the Dutch grid via the 2 GW HVDC link to Maasvlakte.