Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Phase 1 full commercial operations (1 GW) projected for Q2 2030. Phase 1's regulatory deadline is grid-ready by 30 November 2029 (recorded as first_power); commercial operations at full 1 GW typically follow 6-12 months later after final turbine commissioning, hot commissioning of the inter-array system, and full grid handover. Sourced from the Wijzigingsbesluit Phase 1 deadline of 30 November 2029 plus a standard 6-12 month commissioning tail; revisit when Zeevonk confirms commercial operations publicly.