Minor progress or informational
Cadeler's Q1 2026 disclosure provided detailed Hornsea 3 foundation progress as of 20 May 2026: eight monopiles in the water, seven with secondary steel installed, and five fully commissioned. Wind Ally is executing the foundation transport-and-installation scope; Wind Orca is fitting secondary steel. Nearly fifty monopiles have been transported to the marshalling port at Teesworks to date, supported by three chartered Heavy Transport Vessels. CEO Mikkel Gleerup framed the milestone as "proof of concept" on Cadeler's full foundation T&I scope after four years of preparation.