Seaway Heavy Lifting/Seaway7 and Sif completed installation of all 140 TP-less monopile foundations for the 1.5 GW Hollandse Kust Zuid wind farm in the Dutch North Sea. The works were carried out in two campaigns, with 34 foundations installed by December 2021 and the remaining 106 installed in a five‑month campaign in 2022 using the heavy‑lift vessel Seaway Strashnov and an optimised Dynamic Positioning installation method.