Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
DELAYED +3mo (May 2026): Official sources indicate commissioning slips beyond end-2027: OranjeWind’s own timeline shows ‘OranjeWind fully operational’ in 2028, and RWE’s press release expects ‘full commissioning … early 2028’. Therefore full commercial operations should be early 2028 rather than end-2027. --- The OranjeWind offshore wind farm, comprising 53 Vestas V236-15.0 MW turbines with 795 MW installed capacity, is expected to be fully completed and in full commercial operation by the end of 2027, following construction starting in early 2026 and turbine installation commencing in early 2027.