Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 30 July 2020, CrossWind, the Shell–Eneco joint venture developing Hollandse Kust Noord, awarded Van Oord the Balance of Plant EPCI contract covering engineering, procurement, construction and installation of turbine foundations, inter-array cables, and transport and installation of the wind turbines. Van Oord will deploy its offshore installation and cable-lay vessels, including Aeolus, MPI Adventure, MPI Resolution and Nexus, to deliver the 759 MW subsidy-free offshore wind farm planned to be operational in 2023.