On 4 December 2023, Van Oord announced completion of its Balance of Plant (BoP) installation scope at CrossWind's 759 MW Hollandse Kust Noord offshore wind farm. The BoP package covered design, procurement, and installation of 70 TP-less monopile foundations, 140 km of 66 kV inter-array cables, and the 69 Siemens Gamesa SG 11.0-200 DD wind turbines, located 18.5 km off the Dutch coast near Egmond aan Zee. The handover marked completion of Van Oord's EPCI delivery to CrossWind, with the project subsequently entering operations on 20 December 2023.