Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Turbine installation for Golfe de Gascogne Sud (1.2 GW floating, AO10 Sud-Atlantique) is projected to start in 2032 (year precision), typically ~1-2 years after floater/mooring installation. The schedule fits within the 17 October 2024 decision's ~2035 operationality horizon and is consistent with the sibling AO5 floating project Pennavel (turbine installation in 2029-2031 window per pennavel.bzh), shifted forward to reflect AO10's later award timing.