Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Under the AO10 procedural framework — documented in the DIRM Méditerranée briefing (commission spécialisée éolien flottant, 21 February 2025) for the sibling AO10 Golfe du Lion Centre project — the statutory public participation / enquête publique (PPVE) stage is planned during 2027–2028 across the AO10 cohort, with the project-level authorisation (autorisation d'exploiter) issued at or shortly after completion of that stage. For Golfe de Gascogne Sud (1.2 GW floating AO10 Sud-Atlantique), planning consent is projected for 2028 (year precision), in line with the consistent 2028 consent anchor used by sibling AO9/AO10 floating projects in the AgentZero corpus (Golfe du Lion Centre, EFLO). The exact decision date will be determined by the project-specific permitting schedule following the AO10 award.