Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Floater (foundation + mooring/anchor) installation for Golfe de Gascogne Sud is projected to start in 2030 (year precision), the typical first offshore-works phase for a floating wind farm once construction begins. The schedule is consistent with the sibling AO5 floating project Pennavel (foundation/anchoring installation in 2029-2031 per pennavel.bzh "Construction & Installation" phase) and sits within the 17 October 2024 decision's ~2035 operationality horizon. Floater platform type, mooring and anchor specifications are TBC pending the AO10 award.