Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
For the Golfe de Fos offshore wind development area, which includes the future floating wind project Golfe de Fos 2, geophysical, unexploded ordnance (munitions non explosées – UXO), and geotechnical survey campaigns were carried out between December 2022 and July 2023. This timeline implies that UXO survey and investigation activities for the site started in December 2022 as part of a broader package of technical seabed and subsurface studies undertaken during the knowledge-building phase of the project.