Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 25 March 2024, the 71st and final Siemens Gamesa SWT-7.0-154 turbine was installed at the Fécamp offshore wind farm, completing the turbine erection campaign that began with the first unit in July 2023. Installation was carried out by DEME Offshore's heavy-lift jack-up vessel Innovation operating from the port of Cherbourg; Innovation returned to port on the morning of 26 March 2024. By January 2024 more than half of the 71 turbines were in place, with the final 20 units installed over February-March 2024.