Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Prysmian completed and successfully commissioned the 118 km, 33 kV inter-array cable system connecting all 71 turbines to the offshore substation at the Fécamp offshore wind farm, following design, manufacture, installation, burial, termination, and testing of the cables.