Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Prysmian Group secured a contract in 2020 from EDF Renewables and partners for full EPCI delivery of the Fécamp Offshore Wind Farm’s inter-array cable system, covering the design, manufacture, installation, burial, termination and testing of 118 km of 33 kV submarine cables connecting the 71 turbines to the offshore substation.