On 27 June 2025, project company Energa MFW 2 Sp. z o.o. formally initiated the environmental impact assessment procedure for the Energa MFW 2 offshore wind farm in Polish Baltic Sea area 14.E.2. Acting through its representative, the company submitted an application for a decision on environmental conditions for the offshore wind farm and associated infrastructure, together with an application to determine the scope of the EIA report under Article 69 of the Polish Environmental Impact Assessment Act. The competent authority to process this application and issue the environmental decision (DŚU) is the Regional Director for Environmental Protection in Szczecin (RDOŚ Szczecin). This marks the official start of the project’s environmental permitting phase, including cross-border EIA obligations.