RTE carried out the grid connection works for the EFGL floating wind farm, including final cable and grid connection activities ahead of power generation. RTE’s connection scope included the 66 kV export link from the lead turbine to the onshore substation at Saint-Laurent-de-la-Salanque, comprising an approximately 300 m dynamic subsea section followed by about 18 km of buried static subsea cable to landfall, and about 3 km of onshore underground cable to the substation for injection into the national grid.