Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
On 6 November 2019, the Préfet de l'Aude and Préfet maritime de la Méditerranée co-signed arrêté interpréfectoral n° DDTM/DML/UGL/2019310-0001 approving the convention de concession d'utilisation du domaine public maritime naturel (DPMn) between the French State and RTE for the offshore submarine cable corridor of the EFGL floating wind farm grid connection. The DPM concession grants RTE exclusive seabed-use rights for the 63 kV submarine and underground export cable linking the EFGL pilot project off Leucate / Le Barcarès to the Salanques substation. A subsequent avenant n°1 was approved by arrêté interpréfectoral n° DDTM/SML/2022364-0002 of 30 December 2022 (recorded as a separate consent_variation_awarded event).</description> </invoke>