Cadeler's Q1 2026 disclosure confirmed that both Wind Osprey and Wind Pace are now deployed on East Anglia THREE for the turbine installation campaign. Wind Pace was still mobilising from Esbjerg as of 20 April 2026 per ScottishPower Renewables' weekly Notice to Mariners; by Cadeler's 20 May 2026 report both vessels are operational on site, doubling the project's installation throughput.