Project advancing - milestone achieved
High Impact
Major milestone or critical setback
DELAYED +6mo (May 2026): Original projection 2027-12-31 inherited from 2021 tender-era source (source_date 2021-05-01). Latest reporting (power-technology May 2026) puts commercial operation in 2028 — first power typically ~6-12 months ahead of full-power COD; mid-2028 month precision is a defensible anchor. --- In the May 2021 ‘Décision des maîtres d’ouvrage’ (EMD and RTE) following the public debate, the developers state: “La mise en service du parc éolien est prévue en 2027” (commissioning/entry into service planned in 2027). This is taken as the best available developer-stated proxy timeline for first power export.