Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
From mid‑June 2024, TGS began a three‑dimensional ultra high‑resolution seismic (3D UHRS) soil survey over more than 300 km² of the Doordewind Wind Farm Zone under commission from RVO, collecting detailed subsurface data down to about 100 m depth to inform the design of foundations and cable routes for the future 2 GW Doordewind I and II wind farms.