Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Full commercial operations of the 2 GW Doordewind I offshore wind farm are projected for end-2033. The April-2024 Update Aanvullende Routekaart Wind op Zee (Kamerbrief, eerstekamer.nl beslisnota) lists Doordewind kavel I 'Windpark gereed voor leveren vol vermogen' at 31-12-2032 while the matching 2 GW HVDC Doordewind 1 grid connection is delivered 31-03-2033 — meaning the wind farm cannot deliver full nameplate output until the offshore grid link is energised. Persisting full commercial operations at 2033 year-end (year precision) to allow for ramp-up after connection delivery; first power (separate event) remains at Q4 2032 per the same routekaart.