TenneT's Net op Zee Doordewind project page schedules the project decision (projectbesluit) and accompanying permits for the Doordewind 2 (kavel II) offshore grid connection as final by end-2027 under the Rijkscoördinatieregeling, with the appeal window opening at that point. The decision becomes formally irrevocable end-2028 once any appeal period has closed. This event is the GRID-side planning consent; the wind farm itself goes through a separate RVO tender on a different schedule. Event transferred here from the Doordewind II wind farm qc_issue 6a049092 where the agent originally placed it; the source clearly describes Net op Zee Doordewind grid milestones, not wind-farm tender outcomes.