Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
DELAYED +-7mo (May 2026): Le Journal des Entreprises (14 April 2026) reports first turbine installation scheduled May 2026, with turbines operational within 2-3 days of installation. Refining the FID-era 2026-year projection (source 2023-04-26) to May 2026 month-precision with the Apr 2026 article as source. --- Project company Eoliennes en Mer Dieppe Le Tréport (EMDT), led by Ocean Winds with Sumitomo Corporation and Banque des Territoires, states that the 62 Siemens Gamesa 8 MW turbines for the 496 MW Dieppe–Le Tréport offshore wind farm will be installed offshore by Jan De Nul Group during 2026, following completion of foundation and substation works. The turbine installation campaign is planned as part of the three-year construction phase leading to commissioning in the second half of 2026.