Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
DELAYED +0mo (May 2026): Source refresh only. Le Journal des Entreprises (14 April 2026) confirms 'parc entierement mise en service fin 2026' (fully operational by end-2026), reaffirming the FID-era schedule (Apr 2023). Refreshing source_date from 2023-04-27 to 2026-04-14. --- In their April 2023 final investment decision announcements, Ocean Winds (through ENGIE), Sumitomo Corporation and Banque des Territoires, as shareholders of Eoliennes en Mer Dieppe-Le Tréport (EMDT), state that the 62‑turbine, around 500 MW Dieppe-Le Tréport offshore wind farm located 15–17 km off Le Tréport and Dieppe is expected to be commissioned in the second half of 2026, at which point it will be fully operational and able to supply electricity to nearly 850,000 people annually.