Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
In November 2022, EMDT announced it was in exclusive negotiations with DEME for a turnkey contract covering manufacture and installation of the subsea cables connecting the Dieppe–Le Tréport wind turbines to the offshore substation, effectively designating DEME as the preferred EPCI contractor for the project’s inter-array cable system ahead of final contract award.