In 2021, following its 2020 contract to design, manufacture, and install the electrical substation for the Calvados (Courseulles-sur-Mer) offshore wind farm, Atlantique Offshore Energy signed a five-year preventive maintenance contract for the project’s offshore substation. The agreement covers planned maintenance of the 2,100-tonne topside that will collect power from the 64 turbines and transmit it to the onshore substation at Ranville.