Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
DELAYED +0mo (May 2026): Source refresh only — date unchanged. The official Eoliennes en Mer France project page lists 'Date prévue de mise en service: 2032', and the CNDP guarantors' fourth intermediate report similarly cites 2032 as the estimated commissioning year. The 17 February 2026 prefectural environmental authorisation for the grid connection works confirms the project is progressing toward this commissioning target on schedule. --- France's official 'Éoliennes en mer' project page for Centre Manche 1 states: "2032 : Date prévue de mise en service du parc". This 'mise en service' (commissioning/entry into service) is used here as the best available developer/authority-stated timing for first power export in absence of a more granular first-power date.