Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
DELAYED +1yr (May 2026): COD projection at end-2031 appears stale. The official eoliennesenmer.fr project page for Centre Manche 1 lists “Date prévue de mise en service: 2032”. In addition, the CNDP guarantors’ 4th intermediate report lists 2032 as the ‘date estimée de mise en service’ for CM1. To keep the wind farm lifecycle consistent with these updated official/public-planning sources, shift full commercial operation to 2032 (year). --- The Centre Manche 1 offshore wind farm is scheduled to be fully commissioned and enter commercial operation in 2031, in line with the planned 2031 commissioning of its ±320 kV HVDC grid connection to the Menuel 400 kV substation.