Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Floater (foundation + mooring/anchor) installation for Bretagne Nord Ouest (1.2 GW floating, AO10) is projected to start in 2031 (year precision), the year after the offshore construction window opens in 2030. The schedule sits within the 17 October 2024 decision's ~2035 operationality horizon and is consistent with the sibling AO5 floating project Pennavel (foundation/anchoring installation in the 2029-2031 "Construction & Installation" window per pennavel.bzh), shifted ~10 years forward to reflect AO10's later award (end 2026 / early 2027). Floater platform type (spar, semi-sub or TLP), mooring lines and anchor design are TBC pending the AO10 award.