MHI Vestas produced the wind turbines for the Blauwwind Consortium’s Borssele III/IV offshore wind farms in the Dutch North Sea. At financial close, the consortium confirmed that construction and subsequent operation of the project would be based on 77 V164 9.5 MW turbines manufactured by MHI Vestas, contributing to the wind farms’ total installed capacity of 731.5 MW. The turbines referenced were the V164-9.5 MW model, described as the most powerful available turbine at the time. The announcement linked the turbine supply directly to the project’s build programme, noting that main construction work was expected to start in Q4 2019 and that commercial production was expected in early 2021. This role covers manufacture and supply of the full turbine set for Borssele 3 & 4 as stated in the financial close announcement. No contract value, delivery terms, or additional scope elements (such as installation, commissioning, or long-term service/O&M) were specified in the cited source for MHI Vestas beyond turbine production for the 77-unit project.