Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Sif Holding N.V. was awarded a contract by Van Oord to manufacture all 77 monopile foundations, totalling about 68 kton of steel, for the Borssele III & IV offshore wind farm. Under the contract, which is subject to financial close, Sif is to produce the TP-less monopiles for the 731.5 MW project located approximately 22 km off the coast of Zeeland, with fabrication scheduled from early July until December 2018 to support installation of Vestas/MHI Vestas V164‑9.5 MW turbines on monopile foundations without transition pieces.