Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
The Borssele 3 & 4 offshore wind farm exported first power to the Dutch grid on 7 August 2020, after the first of its 77 MHI Vestas 9.5 MW turbines installed at the site began generating electricity. This marked a key construction milestone for the 731.5 MW project in the Dutch North Sea and followed turbine installation that started in May 2020 and grid readiness of TenneT’s 700 MW Borssele Beta platform in late July 2020.