In 2025 Ocean Winds awarded CRIST Offshore the contract to construct the offshore substation for the BC-Wind project. CRIST Offshore, based in Poland, will carry out engineering, construction and commissioning of the offshore substation at the CRIST shipyard in Gdynia, involving around 400 workers. The substation topside, weighing about 2,000 tonnes according to project information, will collect power from the 26 turbines and export it ashore. This supplier selection secures a Tier‑1 Polish yard to deliver the key offshore electrical hub for BC-Wind.