Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
By 2021 Ocean Winds had completed a two‑year wind measurement campaign at the BC‑Wind site. The long‑term measurements, started in 2019, provided high‑quality wind data over the 90.94 km² lease area in Poland’s Baltic Sea Exclusive Economic Zone. Completion of this campaign enabled detailed energy‑yield assessments and refined turbine layout and design assumptions, and it is cited by Ocean Winds as an important milestone alongside securing grid connection and the Contract for Difference (CfD) for the project.