Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In 2025, Ocean Winds secured two Polish installation ports for BC-Wind’s construction logistics: Terminal T5 in Gdańsk for turbine marshalling and Świnoujście Offshore Terminal for foundations. These port arrangements ensure domestic port capacity for storage, pre‑assembly and load‑out of turbines and monopile foundations for the 26‑turbine, 390 MW project in the Baltic Sea, supporting the strategy to deliver BC-Wind fully from Polish ports.