Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Together with the Siemens Gamesa turbine award in July 2025, Ocean Winds confirmed that Cadeler will undertake transportation and installation of the BC-Wind turbines. Cadeler will use its O‑class offshore installation vessels, working from Terminal T5 in the Port of Gdańsk, which will serve as the marshalling harbour for turbine pre‑assembly and load‑out. This contract secures a specialist installation contractor and vessel capacity for the turbine campaign, an important step in locking in construction logistics for the 26‑turbine, 390 MW project.