Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
In 2025, Ocean Winds obtained construction permits (building permits) for both the offshore and onshore parts of the BC-Wind project, enabling the transition into the construction phase. These permits authorise the construction of the wind turbines, foundations and offshore electrical infrastructure, as well as the related onshore facilities. The awarding of these Pozwolenie na budowę decisions followed completion of environmental and transmission permitting and was cited by the developer as coinciding with the Final Investment Decision. Together, they established the full legal basis required under Polish Construction Law to start building the 390 MW bottom-fixed offshore wind farm and its associated onshore infrastructure in the Pomeranian Voivodeship.