Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
Tele-Fonika Kable plans to complete manufacturing of the land export cables for BC-Wind in the fourth quarter of 2026 at its expanded Bydgoszcz plant. The facility is being upgraded with a new 53‑metre CCV tower and additional capacity for high‑ and extra‑high‑voltage cables. All BC-Wind cables and accessories for the onshore export system will be produced there before installation. The schedule foresees cable production for the project in Q4 2026, aligning with the wider onshore construction programme.