Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
On 1 December 2025, Ocean Winds reached Final Investment Decision and financial close for the 390 MW BC‑Wind offshore wind farm in Poland. The developer secured around €2 billion of project finance, backed by the European Investment Bank, Spain’s Instituto de Crédito Oficial and a syndicate of 13–15 international and local commercial banks and hedge providers. This green project‑finance package enables full construction of BC‑Wind, Ocean Winds’ first Baltic Sea project, and confirms the project’s transition from development into the construction phase. The financing is structured as long‑term debt and is underpinned by the project’s 25‑year CfD revenue support.