Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
On 1 July 2025, the Regional Director of Environmental Protection in Gdańsk (RDOŚ Gdańsk) issued an amending Environmental Decision (Decyzja o środowiskowych uwarunkowaniach, DŚU) for the BC-Wind offshore wind farm under reference RDOŚ-Gd-WOO.420.89.2024.AM.7. The amendment modifies the original DŚU of 16 September 2022 (ref. RDOŚ-Gd-WOO.420.50.2021.KSZ.AM.10) issued for the "Morska Farma Wiatrowa BC-Wind" project. Under Polish DŚU practice for offshore wind, substantive amendments to the environmental decision re-emit as a fresh eia_approved event (not as a planning consent variation), since the DŚU sets the binding environmental conditions upstream of the building permit. The decision is immediately enforceable under Offshore Wind Promotion Act 2020 Art. 50-58. The bc-wind.pl document archive lists both the original July 2025 amending decision and a separately-issued supplement; the amending decision underpinned the issuance of building permits and the Final Investment Decision later in 2025.