Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
SPIE Global Services Energy, through its specialist unit SPIE Wind Connect, secured a contract from Seaway7 to perform termination and testing of the 66 kV inter‑array cable systems on the Bałtyk 2 and Bałtyk 3 offshore wind farms. The scope includes pre‑termination testing, routing and cleating of cable cores, installation of fire protection sleeves, fibre‑optic routing and splicing, high‑voltage terminations on the offshore substations and foundations, and post‑termination testing including VLF and partial discharge tests. The main offshore campaign is planned to start towards the end of the second quarter of 2026, with completion in the first half of 2027, supporting final grid connection of the 720 MW Bałtyk 3 project.