Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Installation of the jacket foundations for the two offshore substations serving Bałtyk 2 and Bałtyk 3 is planned for 2026. Equinor and Polenergia have contracted Heerema Marine Contractors to transport and install both wind turbine monopiles and the jackets for the offshore transformer platforms. According to the project schedule, all foundations, including the OSS jackets, will be installed within the 2026 offshore construction campaign at the project sites in the Polish exclusive economic zone of the Baltic Sea.