By late June 2025, preparatory onshore works for the Bałtyk 2 and Bałtyk 3 offshore wind farms’ export cables were underway near Ustka. Within a roughly 14 km onshore connection corridor, Polish contractors were building cable routes and executing trenchless drilling at the landfall using Horizontal Directional Drilling (HDD) technology, allowing the export cables to be installed underground without open trenches. These HDD works and corridor preparations form a key onshore site‑preparation phase for Bałtyk 3’s grid connection ahead of full onshore cable installation and substation construction.