Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Onshore export cable installation for Bałtyk 3 started by June 2025 as part of the shared onshore infrastructure for the Bałtyk 2 and Bałtyk 3 offshore wind farms. Work commenced on constructing approximately 14 km of onshore connection corridor from the landfall near Ustka to the new onshore substations, including trenching and preparing routes for high‑voltage circuits. Polish contractors Enprom and Tele‑Fonika Kable were engaged, with Enprom responsible for building the land cable lines and Tele‑Fonika manufacturing and supplying 220 kV and 400 kV onshore cables. By late June 2025, construction of these power‑cable routes was already underway, marking the effective start of the onshore cable installation campaign for Bałtyk 3.