By 3 July 2025, IQIP had completed transport of sixteen jacket pile grippers to Smulders’ production facility in Newcastle, UK, for integration into the jackets of the two offshore substations serving the Bałtyk 2 and Bałtyk 3 projects. The pile grippers will maintain jacket position and create grouted connections during offshore installation, ensuring structural stability of the OSS platforms. This delivery marks a manufacturing and logistics milestone for Bałtyk 3’s substation foundation components.